Second substation for Dubai solar park

The solar park will contribute to reducing over 6.5 million tons of carbon emissions per year when completed

LinkedInTwitterFacebook
A similar substation to the one which is being installed at Dubai's solar park
A similar substation to the one which is being installed at Dubai's solar park

Dubai’s Mohammed bin Rashid Al Maktoum solar park has taken another important step in integration with the city’s electrical grid.

 

United Arab Emirates leading power utility, Dubai Electricity and Water Authority (DEWA), has awarded an order worth more than $90 million to ABB to build the Shams 400 kV substation that will integrate solar power from upcoming phases of the solar park into the grid.

 

This will be ABB’s second substation for the park, underlining the company’s commitment to deliver reliable power to consumers and serve the building and infrastructure sector alongside utility and industry customers.

 

Following years of rapid growth and urbanisation, Dubai continues to be one of the fastest-growing cities in the world, and booming growth in population and economic sectors, like tourism, have increased demand for energy. To increase power supply and meet goals for increased use of renewables, the UAE launched its ambitious Dubai Clean Energy Strategy 2050 to make Dubai a global centre of clean energy and green economy.

 

The Mohammed bin Rashid Al Maktoum solar park, located inland 50 km south of Dubai, has been a central part of Dubai’s renewable strategy. When completed in 2030, the park will occupy 214 square km, generate 5,000 MW and reduce carbon emissions by approximately 6.5 million tons.

 

ABB is responsible for the design, supply, and installation and commissioning of the Shams 400/ 132 kV substation, which once completed, will have an overall capacity of more than 2,000 megavolt amperes (MVA). When Phase-3 of the project is finished in 2020, which is the same year that Dubai will host Expo 2020, the total solar power generated through solar photovoltaic will exceed 1,000 MW, and significantly lower carbon emissions.

 

Dubai is committed to achieving the objectives of the Dubai Clean Energy Strategy 2050, launched by Sheikh Mohammed bin Rashid Al Maktoum, vice president and Prime Minister of the UAE and Ruler of Dubai, to provide 75 per cent of the Emirate’s total power output from clean energy by 2050.

 

“Meeting the clean energy objectives requires a capacity of 42,000 MW of clean and renewable energy by 2050,” said HE Saeed Mohammed Al Tayer, managing director and CEO of DEWA.

 

“The most prominent project to achieve these objectives, is the Mohammed bin Rashid Al Maktoum Solar Park, which will have a generation capacity of 5,000 MW by 2030, with investments totalling AED50 billion. The solar park will contribute to reducing over 6.5 million tons of carbon emissions per year when completed.”

 

The ABB substation includes supply of 400 and 132 kV gas-insulated switchgear, power transformers, protection, automation and control systems as well as surveillance and communication systems.

 

The substation will also be IEC 61850 enabled, to support open and seamless communication with all intelligent devices. In 2017, ABB delivered its first substation connecting the second phase of the MBR Solar Park and integrating 200 megawatts (MW) of electricity to the transmission grid.

 

If you like this, you might be interested in reading the following:

 

Solar carports help Dubai realise its vision

Dubai Electricity and Water Authority is installing photovoltaic panels at parking lots at its headquarters and at the Ministry of Climate Change and Environment building

Read more

 

Dubai Airports and DEWA work together for Smart Dubai

The airport will play a key part in supporting the Dubai Electricity and Water Authority’s three smart initiatives

Read more

 

Dubai to install smart light poles

Dewa is also investigating solar roads as part of its plan to make Dubai a smart, integrated, and connected city